Insights  /  DCMA 14-Point
DCMA 14-Point

The DCMA 14-Point Assessment, Explained

Almost every owner, prime contractor, and federal agency now judges a construction schedule by the same fourteen tests. Here is what each one measures — and what a failure is actually telling you.

The DCMA 14-Point Assessment came out of the Defense Contract Management Agency as a way to sanity-check a contractor's schedule without re-planning it by hand. Be clear about what it does and doesn't do: it doesn't tell you whether the plan is smart. It tells you whether the schedule is built honestly enough that the dates are worth believing. Those are different questions, and conflating them is where a lot of arguments start.

Fourteen checks. Most carry a pass/fail threshold — miss it and that check fails. Below is what each is looking for, in the order DCMA numbers them, with the standard default threshold. (Owners often tune thresholds to their spec; good software lets you match whatever the contract says.)

How to read the checks

They come in three flavors. Percentage checks tolerate a small share of imperfect activities — usually 5%. Zero-tolerance checks fail on a single instance. And two index metrics — CPLI and BEI — score realism and progress rather than counting defects. Keep the distinction in mind: a 4% reading on a percentage check is a pass; a single negative lag is not.

Checks 1–4: Logic & relationships

Whether the network actually behaves like a network.

Checks 5–7: Constraints & float

Whether the dates are driven by logic or by wishful thinking.

Checks 8–10: Durations, dates & resources

Whether activities are sized and statused so the schedule can be managed.

Checks 11–14: Execution health

Whether the schedule is keeping pace with its own baseline.

What a passing score doesn't tell you

Passing all fourteen doesn't mean the schedule is good. It means it's built cleanly enough to trust the mechanics. A schedule can ace the 14-Point and still sequence work in a way that will never happen in the field — the checks catch dishonesty and sloppiness, not bad strategy. But the reverse is reliably true: a schedule that fails the 14-Point almost always has bigger problems hiding behind the findings. That's why reviewers run it first.

Why it became the standard

Owners and reviewers needed an objective, repeatable screen they could apply to any contractor's file without a week of forensic analysis. The 14-Point gives everyone a common language: "you're failing #5 and #7" is a conversation; "your schedule feels off" is an argument. That objectivity is why it's now written into so many owner and federal schedule specifications — and why schedulers who consistently pass it get less scrutiny on everything else.

ARGUSFORGE

Run all 14 in about two minutes

Drop a .xer export onto ArgusForge and it scores every one of the 14 DCMA checks — each with its metric, threshold, pass/fail, and plain-English fix guidance — alongside nine schedule-quality dimensions, manpower, cost, trend, and Monte Carlo risk. Every threshold is editable to match your contract spec. 100% offline. Your schedule data never leaves your machine.

See ArgusForge

Make it a pre-submit habit

Run the 14-Point on every schedule before it leaves your desk — bids, baselines, monthly updates, claim narratives. Short on time? Start with the zero-tolerance three (#2 Leads, #7 Negative Float, #9 Invalid Dates) and the integrity test (#12); clean those and you've caught the problems that embarrass schedulers in front of owners. For the two findings that trip people up most, we wrote the field playbooks: Leads (#2) and Negative Float (#7).

The 14-Point won't write a good schedule for you. But in about two minutes, it will tell you whether anyone should believe the one you've got.

All insights