Insights  /  Schedule Standards
Schedule Standards

GAO Schedule Assessment: The 10 Best Practices, Explained

Federal agencies, transit authorities, and large infrastructure owners grade schedules against the GAO Schedule Assessment Guide. It asks harder questions than the DCMA 14-Point, and a schedule that sails through DCMA can still fail it.

The U.S. Government Accountability Office wrote the guide to answer one question: can this program's schedule be trusted to predict its finish date? Reviewers apply it to contractors on federal work during oversight. The guide sorts a reliable schedule into four characteristics and grounds each one in specific best practices. Ten in all.

The four characteristics

GAO calls a schedule reliable when it earns four labels: comprehensive, well-constructed, credible, and controlled. Each label rests on best practices you can test against your own file. Miss enough of them and the reviewer downgrades the characteristic, then the schedule.

Comprehensive: the schedule holds all the work

Well-constructed: the logic works

Credible: someone tested the dates

GAO wants a quantitative schedule risk analysis behind the committed date. A single deterministic finish assumes every activity runs to plan, and no project does. Run a Monte Carlo simulation across your durations and logic and you get P-level dates. When the owner pushes on the finish, you answer with a confidence level instead of a promise.

Controlled: the schedule stays current

Where GAO and DCMA diverge

The two standards overlap on logic, constraints, float, and durations. A clean network passes most of both. GAO then asks for three things the DCMA 14-Point skips: resource-loading, a schedule risk analysis, and a maintained baseline with earned-value support. A pure CPM logic schedule that aces DCMA can stall on those three. Find out which standard the owner uses before you build the schedule, not after they hand back the review.

ARGUSFORGE

Score it against both before the owner does

Drop a .xer onto ArgusForge and it grades the schedule against the DCMA 14-Point and the GAO best practices in one pass, with the flagged activities behind every finding. Run the Monte Carlo tab for the risk analysis GAO asks for. Everything runs 100% offline; your schedule never leaves your machine.

See ArgusForge

Run it before the review

Reviewers grade the same file you build, so score it yourself first. Start with the four findings that sink most schedules: a broken critical path, negative float, no baseline, and no risk analysis. Clear those and you walk into the review with a schedule that answers its own questions.

For the checks that overlap most with GAO's logic requirements, read our field guides to leads and negative lags and the full DCMA 14-Point breakdown.

All insights